Planned Interruptions

Planned interruptions are those electric power distribution cut-offs caused by development or maintenance  works.

According to the requirements of performance standard for electric power distribution service,  Art. 11(1):,,In case of development and maintenance works, the Distribution Operator, together with the Users, shall  agree/ find  a scheduling convenient to both parties.

The distribution operator must notify all users with regard to the date, time and interval of required down-time, with minimum 15 working days prior to the works commencement date.